Preparation & planning a consulting assignment



Category: Training

Plan activities and tasks

Plan time

Plan HR

In this regard Gantt Charts are very useful. In can be drown both: manually as well as using a computer. Microsoft Project is powerful software used to plan projects.

Example of a simple Gantt Chart

Example of a simple Gantt Chart

Example of a consulting project plan using Microsoft Project.

Example of a consulting project plan using Microsoft Project

Estimate costs

Example of a budget for a training course

Budget for the project «Implementation of 20 keys management system

HACCP & ISO 9001 to ABC JSC»

Period: 1.12.03 — 30.11.04 Duration 12 months

USD

# Item Position Nr. of units Price per unit Value
1 Contracts amount contracts 3 24500
2 including:
3 ISO 9001 days 35 140 4900
4 HACCP days 47 140 6580
5 20 keys days 77 140 10780
6 Project Management days 9 250 2240
7 Company gross profit margin % 30% 7350
8 Bonus for selling the project % 10% 2450
9 including: %
10 Valentin Sverdlic % 10% 600
11 Dinu Gutu % 10% 1850
12 Operational expenses % 60% 14700
13 Transportation tur retur 50 20 1000
14 Consumables copies 5000 0.03 150
15 Labor:
16 Gross Salaries 13550
17 Net salaries 7612.36
18 including:
19 Dinu Alexei ISO Consultant 35 43.50 1522.47
20 Ion Bostan HACCP Consultant 47 43.50 2044.46
21 Andrei Cojocari 20 keys Consultant 77 43.50 3349.44
22 Andrei Cojocari MP 8.96 77.68 695.99
23 Taxes 5937.64

Note: A 25% discount was offered to the client because of contracting 3 products at once and assuring 30% advance payment

Note: Agree the plan & budget with company this is part of he proposal and the contract.


« ||| »